# Lab Timesheet — Three-Iteration Delivery Plan
|
||
|
||
**Artifact purpose:** Local agent coordination and progress tracking
|
||
**Implementation branches:** `work/platform`, `work/projects`, `work/tasks`, `work/attendance`, `work/reports-ui`
|
||
**Requirements authority:** `labtimesheet-docs-hub/requirements-specification.md`
|
||
**SRS:** `labtimesheet-docs-hub/software-requirements-specification.md`
|
||
**Initial status:** Planning complete; implementation remains subject to requirements approval
|
||
|
||
This file divides the approved product scope across three iterations and five persistent work branches. It is a coordination artifact, not an alternative requirements source. When this plan and a numbered requirement disagree, the numbered requirement wins.
|
||
|
||
## 1. Progress rules
|
||
|
||
Use these exact status values:
|
||
|
||
| Status | Meaning |
|
||
|---|---|
|
||
| `TODO` | No implementation work has started. |
|
||
| `IN_PROGRESS` | One named owner is actively working on the item. |
|
||
| `BLOCKED` | Work cannot continue; the tracker must name the evidence and required decision/dependency. |
|
||
| `DONE` | Required RED/GREEN evidence exists, affected tests pass, and the integrated behavior satisfies the requirement. |
|
||
|
||
Before editing production code, an agent shall:
|
||
|
||
1. Read the applicable numbered requirements and acceptance scenarios.
|
||
2. Claim one bounded tracker item by setting its status to `IN_PROGRESS` and recording owner/date.
|
||
3. Identify the test level and evidence file that will protect the behavior.
|
||
4. Write and run the failing test before production code.
|
||
5. Confirm the test fails because the required behavior is missing, not because the test or environment is broken.
|
||
|
||
When completing an item, the agent shall record:
|
||
|
||
- the exact RED command and expected failure;
|
||
- the exact GREEN and affected-suite commands;
|
||
- the evidence Markdown path under `docs/tests/`;
|
||
- the implementation commit or final local commit SHA;
|
||
- any remaining limitation that is explicitly allowed by the requirements.
|
||
|
||
No item becomes `DONE` based only on compilation, an isolated happy path, screenshots, or a verbal claim.
|
||
|
||
## 2. Branch ownership and conflict boundaries
|
||
|
||
| Branch | Sole or primary ownership |
|
||
|---|---|
|
||
| `work/platform` | Maven/application baseline, feature-package foundation, Flyway migration files, account/security/bootstrap, internship lifecycle, integration credential lifecycle, notification delivery infrastructure, Docker, and CI. |
|
||
| `work/projects` | Projects, membership intervals, invitations, membership-exit requests/readiness, leadership terms, Project lifecycle, Project-history authorization, transfer orchestration, and Project completion. |
|
||
| `work/tasks` | Tasks, generic creator/assignment actors, pending-exit assignment exclusion, member self-Task rules, comments, work logs, fixed status transitions, batch reassignment/direct-removal transfer operations, Task soft deletion, and Project Task-progress/history queries. |
|
||
| `work/attendance` | Attendance-policy versions/history, configured workdays, global calendar/history, HolidayAPI import interpretation, attendance, corrections, leave, deadline schedulers, and attendance/compliance metrics. |
|
||
| `work/reports-ui` | Shared Thymeleaf shell/fragments, Tailwind tokens/assets, dashboards, invitation/exit/transfer screens, Project and Admin-setting History tabs, shared report datasets, Chart.js presentation, XLSX/PDF exports, and cross-product UI/accessibility consistency. |
|
||
|
||
Conflict-prevention rules:
|
||
|
||
- `LabtimesheetApplication` shall remain in `com.lab.labtimesheet`, shared wiring in `config`, and business code in `feature.account`, `feature.integration`, `feature.project`, `feature.task`, `feature.attendance`, `feature.notification`, or `feature.reporting`. Each feature repeats only the controller/model/model.dto/model.entity/repository/service/exception layers it needs, and tests mirror that feature/layer shape.
|
||
- Cross-feature code may call another feature's service contract and DTOs but shall not import that feature's repository or JPA entity. Do not create empty `utils`, `common`, or `core` packages.
|
||
- Business persistence shall use Spring Data JPA repositories. Direct SQL is limited to Flyway migrations and schema/catalog verification; services shall not use `JdbcTemplate` or embed SQL.
|
||
|
||
- `work/platform` owns `src/main/resources/db/migration/**`, Maven/dependency configuration, Compose, container build files, and CI workflow files. Other branches request schema changes instead of independently allocating migration versions.
|
||
- `work/reports-ui` owns shared templates/fragments, shared design tokens, and general UI assets. Each domain branch owns its module-specific controllers and pages while consuming those shared fragments.
|
||
- A targeted repair shall use a clean, isolated `work/fix/<feature>/<what-fix>` branch and worktree from the taskmaster-verified current `main`. Do not use `work/<feature>/fix/<what-fix>`: the persistent `work/<feature>` ref already occupies that Git ref prefix.
|
||
- `work/tasks` exposes focused Task eligibility, batch-transfer, unfinished-count, and retained-history operations required by Project workflows. `work/projects` owns pending-exit readiness/approval, direct-removal orchestration, and Project completion transactions.
|
||
- `work/platform` owns HolidayAPI credential storage and the tested HTTP client. `work/attendance` owns preview interpretation, selection, deduplication, import, and day-off effects.
|
||
- Attendance time and Task work time remain separate. No branch may make one mutate or prove the other.
|
||
- Do not introduce a generic workflow engine, generic event-sourcing layer, multi-assignee Task model, Project-level day-off model, or speculative cross-module abstraction.
|
||
|
||
## 3. Iteration overview
|
||
|
||
| Iteration | Theme | Required demonstration | Status | Integration commit |
|
||
|---|---|---|---|---|
|
||
| 1 | Working vertical slice | Bootstrap users, create/activate Project, assign/change a Task, and check in/out with role-correct UI. | `DONE` | `b9b150ff8ca9333e3b46d77537ec91875a970d57` |
|
||
| 2 | Complete business workflows | Policy/calendar changes, leave/corrections, leadership/member transfer, work logs, notifications, and full HTML workflows. | `TODO` | — |
|
||
| 3 | Hardening and delivery | Historical/concurrency proof, production security, HTML/XLSX/PDF parity, accessibility, containers, and CI publication boundary. | `TODO` | — |
|
||
|
||
## 4. Iteration 1 — Working vertical slice
|
||
|
||
### 4.1 `work/platform`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I1-PLAT-01 | Establish the Maven/Spring Boot modular baseline and root/config/feature package boundaries. | Context/load test; root-package and package-by-feature/layer check; no cross-feature repository/entity access or direct-SQL business services. | `DONE` | platform_agent / 2026-08-15 | Approved Platform head `692b23e9b9891d360882671d8247965b44920b2f`; integrated architecture/full-suite gates passed. |
|
||
| I1-PLAT-02 | Promote the reviewed 23-table/56-foreign-key PostgreSQL baseline into the platform-owned initial Flyway migration after explicit approval. | Fresh PostgreSQL 18.4 migration replay, catalog assertions, and invitation/exit same-Project constraints. | `DONE` | platform_agent / 2026-08-15 | Fresh local replay produced exactly 23 application tables and 56 foreign keys at the integrated head. |
|
||
| I1-PLAT-03 | Configure PostgreSQL Testcontainers and shared test-only encryption/clock facilities. | Affected integration tests require no developer database or SMTP. | `DONE` | platform_agent / 2026-08-15 | Taskmaster full PostgreSQL 18.4 Testcontainers suite passed 197/197. |
|
||
| I1-PLAT-04 | Implement atomic first-Admin bootstrap and permanent bootstrap closure. | Concurrent submissions create exactly one first Admin; restart keeps bootstrap closed. | `DONE` | platform_agent / 2026-08-15 | Bootstrap/restart/concurrency evidence approved at `692b23e9b9891d360882671d8247965b44920b2f`; fresh local bootstrap passed. |
|
||
| I1-PLAT-05 | Implement initial SMTP draft/test/active path sufficient for Mailpit onboarding. | Failed test cannot activate; tested revision supports delivery. | `DONE` | platform_agent / 2026-08-15 | Real local Mailpit draft, test delivery, activation, active-state, and health checks passed at the integrated head. |
|
||
| I1-PLAT-06 | Create Mentor/Intern accounts, deliver activation, set first password, and authenticate/logout. | SMTP gate, single-use token, expiry, normalized email, role/state access. | `DONE` | platform_agent / 2026-08-15 | Activation/authentication evidence and independent review approved at `692b23e9b9891d360882671d8247965b44920b2f`. |
|
||
| I1-PLAT-07 | Provide development Compose with PostgreSQL and Mailpit plus initial Gitea verification workflow. | Fresh developer start and branch/main verification. | `DEFERRED` | taskmaster / 2026-08-15 | Explicitly excluded from this exit gate; application containerization, Compose, and CI remain future work. |
|
||
|
||
### 4.2 `work/projects`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I1-PRJ-01 | Atomically create a Mentor-owned `PLANNED` Project, eligible initial Leader membership, and first leadership term. | No committed Project is empty or leaderless; non-owner, ineligible Leader, and guessed-ID access are denied. | `DONE` | projects_agent / 2026-08-15 | Approved Project head `baa0695c60153bc997ebf8b11adcfbdd2cbc1962`; Project suite and review passed. |
|
||
| I1-PRJ-02 | Directly add eligible Interns through owning-Mentor-controlled interval memberships. | Multiple concurrent Projects per Intern; duplicate active membership rejected; no acceptance step for direct add. | `DONE` | projects_agent / 2026-08-15 | Membership/eligibility/IDOR evidence approved at `baa0695c60153bc997ebf8b11adcfbdd2cbc1962`. |
|
||
| I1-PRJ-03 | Appoint and change one current Leader from active same-Project members. | One current Leader; non-member/ineligible selection rejected. | `DONE` | projects_agent / 2026-08-15 | Leadership-term invariants and completed-history behavior approved at `baa0695c60153bc997ebf8b11adcfbdd2cbc1962`. |
|
||
| I1-PRJ-04 | Activate a Project when initial member, Leader, date, and assignee guards pass. | Missing Leader/member or invalid assignee blocks activation. | `DONE` | projects_agent / 2026-08-15 | Task-bound activation guard approved at `baa0695c60153bc997ebf8b11adcfbdd2cbc1962`. |
|
||
| I1-PRJ-05 | Provide Project list/detail/member/leadership pages with owning-Mentor and member visibility. | MockMvc authorization plus direct-ID denial. | `DONE` | projects_agent / 2026-08-15 | Authorized pages, retained errors, and former-member history approved at `baa0695c60153bc997ebf8b11adcfbdd2cbc1962`. |
|
||
|
||
### 4.3 `work/attendance`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I1-ATT-01 | Resolve the seeded attendance policy, timezone, configured workdays, schedule, and separate check-in/checkout grace boundaries. | Both grace defaults are 30; values are 0–720; checkout cutoff must stay before local midnight. | `DONE` | attendance_agent / 2026-08-15 | Approved Attendance head `01b8095e9459417e2cf5bd1079c796d4f01ec549`; fresh seed verified both grace values at 30. |
|
||
| I1-ATT-02 | Manage manual future global calendar events and day-off decisions. | Admin-only mutation; past-event immutability; workday/day-off distinction. | `DONE` | attendance_agent / 2026-08-15 | Calendar authorization and day-off evidence approved at `01b8095e9459417e2cf5bd1079c796d4f01ec549`. |
|
||
| I1-ATT-03 | Check in once on an eligible day using server time and the effective policy. | Off-day, approved-leave, duplicate, lifecycle rejection, and inclusive 09:00 check-in-grace boundary. | `DONE` | attendance_agent / 2026-08-15 | Boundary, eligibility, leave-day, and real duplicate-race evidence approved at `01b8095e9459417e2cf5bd1079c796d4f01ec549`. |
|
||
| I1-ATT-04 | Check out once through the attached-policy checkout cutoff and derive basic daily classification. | Default 16:00 succeeds; first later instant and zero-grace late attempt fail; no checkout becomes only `MISSING_CHECKOUT` with raw checkout unchanged. | `DONE` | attendance_agent / 2026-08-15 | Historical-policy cutoff, eligibility recheck, and missing-checkout-only evidence approved at `01b8095e9459417e2cf5bd1079c796d4f01ec549`. |
|
||
| I1-ATT-05 | Provide own-attendance history and authorized Mentor/Admin inspection. | Own/global-view authorization and historical applied-policy display. | `DONE` | attendance_agent / 2026-08-15 | Policy-local history, all violations, and role authorization approved at `01b8095e9459417e2cf5bd1079c796d4f01ec549`. |
|
||
|
||
### 4.4 `work/tasks`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I1-TSK-01 | Create one-assignee Tasks in `PLANNED` or `ACTIVE`: any active member for self, current Leader for any active same-Project member. Store generic creator/assigner/assignee actors. | Self-Task actor equality, other-assignee denial for members, Leader allowance, and cross-Project actor rejection. | `DONE` | tasks_agent / 2026-08-15 | Approved Task head `e38e2cdea912160b183c65398c4e8d5682c1b00e`; actor/assignee/IDOR evidence passed review. |
|
||
| I1-TSK-02 | Validate optional due dates against Project dates and current global days off. | Boundary dates accepted; outside/day-off dates rejected. | `DONE` | tasks_agent / 2026-08-15 | Due-date/calendar validation and retained field-error behavior approved at `e38e2cdea912160b183c65398c4e8d5682c1b00e`. |
|
||
| I1-TSK-03 | Enforce the complete fixed Task status graph through current-assignee authorization. | Parameterized allowed/forbidden transition matrix and ID denial. | `DONE` | tasks_agent / 2026-08-15 | Server graph and legal UI choices approved at `e38e2cdea912160b183c65398c4e8d5682c1b00e`. |
|
||
| I1-TSK-04 | Add append-only Task comments for active members, current Leader, and owning Mentor. | Unauthorized/non-member and completed-Project mutation denial. | `DONE` | tasks_agent / 2026-08-15 | Comment authorization, lock order, and completed-history behavior approved at `e38e2cdea912160b183c65398c4e8d5682c1b00e`. |
|
||
| I1-TSK-05 | Show Task list/detail and initial DONE/non-deleted progress/status counts. | Empty Project renders `N/A`; soft/deleted data not yet exposed as current. | `DONE` | tasks_agent / 2026-08-15 | Progress/N/A, assignee display, visibility, and dashboard ordering approved at `e38e2cdea912160b183c65398c4e8d5682c1b00e`. |
|
||
|
||
### 4.5 `work/reports-ui`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I1-UI-01 | Establish Tailwind tokens and reusable Thymeleaf shell/fragments. | Fragment rendering, local assets, no unauthorized navigation items. | `DONE` | reports_ui_agent / 2026-08-15 | Shared local-asset shell and persistent SMTP restriction contract verified at `039fe25c7c2622a015c8962892dd99ff58be321d`. |
|
||
| I1-UI-02 | Implement the supported desktop sidebar/header, forms, tables, badges, alerts, confirmations, empty/error states, and theme bootstrap. | Keyboard labels/focus, no desktop page-level overflow, pre-paint theme application. | `DONE` | reports_ui_agent / 2026-08-15 | Edge/Chromium 1365x900 focus, collapse tooltip, theme pre-paint, and overflow gates verified at `039fe25c7c2622a015c8962892dd99ff58be321d`. |
|
||
| I1-UI-03 | Build basic Admin, Mentor, and Intern dashboards from real queries. | Role-correct metrics/actions; illustrative data never leaks into production paths. | `DONE` | reports_ui_agent / 2026-08-15 | Public service/DTO dashboards and role-correct navigation verified at `039fe25c7c2622a015c8962892dd99ff58be321d`. |
|
||
| I1-UI-04 | Integrate bootstrap, authentication, Project, Task, and attendance pages into the shared shell. | Critical MockMvc web flows and server-side authorization. | `DONE` | reports_ui_agent / 2026-08-15 | Integrated shell, SMTP five-step journey, forms, history, errors, and authorization verified at `039fe25c7c2622a015c8962892dd99ff58be321d`. |
|
||
|
||
### 4.6 Iteration 1 integration gate
|
||
|
||
Integration order:
|
||
|
||
1. `work/platform`
|
||
2. `work/projects`
|
||
3. `work/attendance`
|
||
4. `work/tasks`
|
||
5. `work/reports-ui`
|
||
|
||
Exit demonstration:
|
||
|
||
- First Admin bootstraps the installation.
|
||
- SMTP is tested through Mailpit.
|
||
- Admin creates and activates Mentor and Intern accounts.
|
||
- Mentor atomically creates a Project with its first Leader, directly adds another member, and activates it.
|
||
- Ordinary member creates a self-assigned Task; Leader creates and assigns another Task.
|
||
- Assignee changes Task status and comments.
|
||
- Intern checks in and checks out.
|
||
- Every role sees only authorized navigation, actions, and records.
|
||
- Full integrated tests pass at the iteration integration commit.
|
||
|
||
Taskmaster exit result (2026-08-15): `DONE` at main integration commit `b9b150ff8ca9333e3b46d77537ec91875a970d57`, incorporating reviewed candidate `039fe25c7c2622a015c8962892dd99ff58be321d` and the verified development configuration/documentation follow-up. The final merged-main PostgreSQL 18.4 suite passed 197/197; Flyway produced 23 application tables and 56 foreign keys; Node 24/Tailwind assets built successfully; compile and full Javadoc/doclint passed on the reviewed candidate. A real local Java 25 process completed fresh bootstrap, login, five-step SMTP deferral, persistent restriction recovery, and a separate real Mailpit draft/test/activate flow with aggregate health `UP`. Temporary exit databases and Mailpit were removed; the existing development PostgreSQL service remained intact. Project/Task/Attendance role flows are protected by the approved branch suites and real desktop E2E evidence. Application containerization, Compose, CI, and production liveness/readiness hardening remain deferred as recorded above.
|
||
|
||
## 5. Iteration 2 — Complete business workflows
|
||
|
||
Iteration 2 starts only after every continuing branch incorporates the integrated Iteration 1 `main`.
|
||
|
||
### 5.1 `work/platform`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I2-PLAT-01 | Complete account lock/unlock/deactivation and session invalidation. | State graph, authentication denial, retained attribution. | `TODO` | — | — |
|
||
| I2-PLAT-02 | Implement activation failure/resend and forgot/reset-password workflows. | Failed token invalidation, single-use/expiry, generic enumeration-safe responses. | `TODO` | — | — |
|
||
| I2-PLAT-03 | Implement internship start activation, completion, and withdrawal guards. | Scheduler plus request-time activation; Leader/unfinished-Task terminal guards. | `TODO` | — | — |
|
||
| I2-PLAT-04 | Complete encrypted SMTP and HolidayAPI draft/test/active revision lifecycles. | AES-GCM round trip, wrong-key failure, one active revision, no browser secret disclosure. | `TODO` | — | — |
|
||
| I2-PLAT-05 | Expose the tested VN HolidayAPI client to the attendance module. | Valid preview, invalid key/rate limit/unavailable responses without local-data outage. | `TODO` | — | — |
|
||
| I2-PLAT-06 | Persist in-app notifications and initial ordinary-email delivery states, including Project invitation and membership-exit created/resolved types. | Recipient deduplication, domain commit independent of SMTP, self-Task silence, and `UNAVAILABLE`/sent/failed behavior. | `TODO` | — | — |
|
||
|
||
### 5.2 `work/tasks`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I2-TSK-01 | Add dated 1–1440-minute Task work logs and author corrections. | Membership/date boundaries and author-only editing. | `TODO` | — | — |
|
||
| I2-TSK-02 | Enforce the combined 1440-minute daily total across all Projects. | PostgreSQL integration and concurrent over-allocation proof. | `TODO` | — | — |
|
||
| I2-TSK-03 | Reassign unfinished Tasks while preserving creator, state, comments, work logs, lifecycle timestamps, and assignment actor/time; exclude pending exit targets from new/self-assignment. | DONE requires assignee reopen; prior attribution remains; pending target keeps existing assignee rights but receives no new work. | `TODO` | — | — |
|
||
| I2-TSK-04 | Implement Task edit/soft deletion and authorized historical inspection for Leader/self-Task creator plus Project History projection. | Eligible creator controls only while current assignee; deleted/completed Tasks expose retained attribution without invented previous-assignee or edit/status timelines. | `TODO` | — | — |
|
||
| I2-TSK-05 | Provide repeatable multi-Task/one-recipient transfer batches, unfinished-count, direct-removal transfer, and completion-query operations to Projects. | Each batch is atomic; recipient/pending state rechecked; direct removal transfers all unfinished Tasks atomically; non-deleted/DONE counts remain correct. | `TODO` | — | — |
|
||
| I2-TSK-06 | Complete Project status counts, percentage, total minutes, and per-member work queries. | Empty `N/A`, authorization scopes, hand-checkable totals. | `TODO` | — | — |
|
||
|
||
### 5.3 `work/projects`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I2-PRJ-01 | Issue and revoke non-expiring Leader invitations while retaining the issuing leadership term. | Eligibility, one pending Project/Intern pair, Leader-own versus Mentor-any revocation, ordinary notification behavior. | `TODO` | — | — |
|
||
| I2-PRJ-02 | Let only the intended authenticated Intern accept or decline; support Mentor direct-add supersession. | Email is not a bearer join token; exactly one membership; terminal status/code and provenance retained. | `TODO` | — | — |
|
||
| I2-PRJ-03 | Create/cancel Leader-removal and member-leave requests, expose persistent readiness warnings, and keep existing rights while excluding the target from new/self-assignment. | Nonblank reason, same-Project/type shape, one pending request per target, requester-only cancellation, replacement/remaining/ready state for every authorized viewer. | `TODO` | — | — |
|
||
| I2-PRJ-04 | Let only the owning Mentor approve/reject exits after Leader-managed redistribution; preserve the direct-removal automatic-transfer shortcut. | Leader exit requires replacement first; repeated batches persist; cancel/reject keeps them and restores eligibility; approval waits for non-Leader/zero unfinished Tasks; closure/request resolution commit together. | `TODO` | — | — |
|
||
| I2-PRJ-05 | Retain leadership history, change Leader without moving assignments, and complete only when every non-deleted Task is `DONE`. | Exactly one current Leader in PLANNED/ACTIVE; completion closes intervals, revokes invitations, and supersedes exits. | `TODO` | — | — |
|
||
| I2-PRJ-06 | Provide one authorized Project History view for membership, leadership, invitation, exit decision, completed/soft-deleted Task, comment, work-log, and retained attribution data. | Admin all read-only; owning Mentor/current member on open Project; removed member denied until completion; no fabricated previous-assignee/status/edit timeline. | `TODO` | — | — |
|
||
|
||
### 5.4 `work/attendance`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I2-ATT-01 | Schedule future-month attendance-policy versions, including separate grace values, preserve effective history, and expose Admin-only Policy History. | First-of-future-month rule; effective immutability; old cutoff/report stability; safe version/actor/effective metadata only. | `TODO` | — | — |
|
||
| I2-ATT-02 | Preview/import VN HolidayAPI candidates with Admin selection, override, provenance, deduplication, and Admin-only Calendar History. | Public suggestion not authority; manual fallback; repeated import safety; past/current event metadata remains read-only and non-secret. | `TODO` | — | — |
|
||
| I2-ATT-03 | Materialize frozen full-day leave allocations and monthly/cross-month quota reservations. | Workday/day-off classification, policy snapshot, quota per month. | `TODO` | — | — |
|
||
| I2-ATT-04 | Implement leave submit/approve/reject/cancel and overlap protection. | Same-day boundary, pending/approved reservations, concurrent overlap/quota. | `TODO` | — | — |
|
||
| I2-ATT-05 | Implement missed-checkout correction submission and effective-checkout derivation. | Reject before/at checkout cutoff; accept afterward through scheduled end +24 hours; raw checkout remains null. | `TODO` | — | — |
|
||
| I2-ATT-06 | Implement Mentor approve/reject/revert and separate decision-window locking. | Valid state graph, concurrent decision, expired pending auto-rejection. | `TODO` | — | — |
|
||
| I2-ATT-07 | Add idempotent schedulers and equivalent request-time deadline guards. | Late/multiple scheduler invocation cannot duplicate transitions/notifications. | `TODO` | — | — |
|
||
|
||
### 5.5 `work/reports-ui`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I2-UI-01 | Complete Admin/Mentor/Intern/Leader dashboards and notification UI. | Authorization-correct actions and deadline/state summaries. | `TODO` | — | — |
|
||
| I2-UI-02 | Complete account, integration, Project, invitation, membership-exit/transfer, Task, policy/calendar, attendance, correction, leave, and History desktop workflows using shared fragments. | Persistent warning; Leader-only multi-Task/one-recipient drawer; Mentor readiness decision; Project History; Admin-only Policy/Calendar/SMTP/HolidayAPI History; keyboard operation, redaction, and clear conflicts. | `TODO` | — | — |
|
||
| I2-UI-03 | Build one authorized attendance/compliance HTML report dataset. | Date filters, detailed versus own scope, formulas and `N/A`. | `TODO` | — | — |
|
||
| I2-UI-04 | Build one authorized Project/Task HTML report dataset. | Project/member/status/date filters and per-member visibility rules. | `TODO` | — | — |
|
||
| I2-UI-05 | Add only meaningful Chart.js trends with adjacent text/table alternatives. | Accessible label, equivalent data, theme tokens, reduced motion. | `TODO` | — | — |
|
||
|
||
### 5.6 Iteration 2 integration gate
|
||
|
||
Integration order:
|
||
|
||
1. `work/platform`
|
||
2. `work/tasks`
|
||
3. `work/projects`
|
||
4. `work/attendance`
|
||
5. `work/reports-ui`
|
||
|
||
Exit demonstration:
|
||
|
||
- Admin schedules a future policy without changing historical output.
|
||
- Admin previews/imports holidays and overrides a suggested day-off decision.
|
||
- Intern submits cross-month leave and Mentor decides it.
|
||
- Intern submits a missed-checkout correction; Mentor decides and may revert it inside the window.
|
||
- Leader reassigns an unfinished Task while preserving creator, comments, work logs, and current assignment attribution.
|
||
- Leader invites an eligible Intern; the signed-in Intern accepts or declines; Mentor direct-add safely supersedes a pending invite.
|
||
- Mentor changes Leader without moving the former Leader's Tasks.
|
||
- Member requests to leave and Leader requests removal; all authorized viewers see readiness, replacement is appointed first when needed, Leader redistributes unfinished Tasks in repeated batches, cancellation/rejection keeps completed batches, and approval waits for zero unfinished Tasks.
|
||
- Mentor directly removes an ordinary member and a Leader in separate cases; automatic transfer remains atomic and completed Tasks keep the removed Intern's displayed name.
|
||
- Admin, owning Mentor, current member, and removed member before/after completion receive the exact Project History visibility defined by AUTH-006.
|
||
- Admin opens read-only Attendance Policy, Calendar, SMTP, and HolidayAPI History tabs; non-Admins are denied and no secret/internal retry data appears.
|
||
- Mentor completes a Project after all non-deleted Tasks are done.
|
||
- Ordinary domain actions retain in-app notifications when SMTP is unavailable.
|
||
- Full integrated tests pass at the iteration integration commit.
|
||
|
||
## 6. Iteration 3 — Hardening, reports, and delivery readiness
|
||
|
||
Iteration 3 starts only after every continuing branch incorporates the integrated Iteration 2 `main`.
|
||
|
||
### 6.1 `work/platform`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I3-PLAT-01 | Add normalized-email-plus-source-IP login throttling. | Five-in-15 and 15-minute throttle boundaries; successful-login clearing. | `TODO` | — | — |
|
||
| I3-PLAT-02 | Finish ordinary email retry schedule and terminal failure handling. | Exact 1m/5m/30m/2h/12h attempts; idempotent bounded worker. | `TODO` | — | — |
|
||
| I3-PLAT-03 | Add token cleanup and production-safe operational/status views. | Expired token behavior, no secret/stack/SQL disclosure. | `TODO` | — | — |
|
||
| I3-PLAT-04 | Enforce production HTTPS/origin/proxy/header/cookie/master-key readiness. | Prod fails unsafe configuration; dev/test relax only transport/origin controls. | `TODO` | — | — |
|
||
| I3-PLAT-05 | Produce the non-root application image and bundled/external PostgreSQL deployment modes. | Same immutable image becomes healthy in both configurations. | `TODO` | — | — |
|
||
| I3-PLAT-06 | Finalize Gitea verification, main-only OCI publication, and disabled SSH deployment/rollback template. | Work branches never publish; disabled deploy receives no secrets; exact-SHA flow is testable when enabled. | `TODO` | — | — |
|
||
|
||
### 6.2 `work/projects`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I3-PRJ-01 | Harden concurrent membership, invitation acceptance/direct-add, exit approval, and leadership operations. | One valid winner; locks/rechecks cover invitation, Project, membership, leadership, request, and unfinished Tasks; stale requests produce explicit conflict without partial history. | `TODO` | — | — |
|
||
| I3-PRJ-02 | Complete the global-role/context/ownership authorization matrix for direct membership, invitations, exits, and leadership. | Direct-ID, stale Leader, wrong invitee, cross-Mentor/member, requester, target, and decision-maker negative cases. | `TODO` | — | — |
|
||
| I3-PRJ-03 | Prove completed/historical read-only behavior and terminal Intern guards. | No mutation through UI or direct request after lifecycle closure. | `TODO` | — | — |
|
||
| I3-PRJ-04 | Verify Project list/progress query indexes and bounded performance. | Explain plan/catalog evidence for actual report paths. | `TODO` | — | — |
|
||
|
||
### 6.3 `work/tasks`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I3-TSK-01 | Harden concurrent status, reassignment, deletion, and daily-minute operations. | Optimistic conflicts and serialized daily total. | `TODO` | — | — |
|
||
| I3-TSK-02 | Complete due-date impact behavior for later-created global days off. | Existing due date retained and disclosed; new/changed due date rejected. | `TODO` | — | — |
|
||
| I3-TSK-03 | Complete former-assignee work-log correction and historical-deletion boundaries. | Author/member/Project lifecycle matrix. | `TODO` | — | — |
|
||
| I3-TSK-04 | Complete Task authorization/ID-guessing matrix and progress query verification. | Admin/Mentor/Leader/member/creator/current-assignee distinctions, creator-right loss after reassignment, generic same-Project actors, and real query indexes. | `TODO` | — | — |
|
||
|
||
### 6.4 `work/attendance`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I3-ATT-01 | Finalize attendance-rate and compliance formulas plus `N/A` denominators. | Hand-derived expected values across absence, leave, days off, and violations. | `TODO` | — | — |
|
||
| I3-ATT-02 | Prove historical stability after workday, schedule, check-in/checkout grace, quota, penalty, and calendar changes. | Before/after report equality plus unchanged cutoff for an older attendance row. | `TODO` | — | — |
|
||
| I3-ATT-03 | Harden concurrent leave quota/overlap and correction-decision races. | PostgreSQL exclusion plus transactional locking/optimistic conflicts. | `TODO` | — | — |
|
||
| I3-ATT-04 | Prove request-time and scheduler equivalence at checkout/correction boundaries and both expiry windows. | Pre-cutoff correction rejection; inclusive submission deadline; delayed/repeated scheduler produces one final transition. | `TODO` | — | — |
|
||
| I3-ATT-05 | Complete terminal-Intern and date-classification edge cases. | Terminal date with/without attendance, approved leave, and global day off. | `TODO` | — | — |
|
||
|
||
### 6.5 `work/reports-ui`
|
||
|
||
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|
||
|---|---|---|---|---|---|
|
||
| I3-UI-01 | Export attendance/compliance and Project/Task datasets to XLSX. | Parse workbook and compare filters, rows, totals, and `N/A` with HTML. | `TODO` | — | — |
|
||
| I3-UI-02 | Export the same datasets to PDF through a print-safe template and embedded Unicode font. | Vietnamese sample text and HTML/XLSX/PDF total parity. | `TODO` | — | — |
|
||
| I3-UI-03 | Complete desktop light/dark themes and all required desktop screens/states. | Theme before paint, system override, contrast, error/empty/stale/unavailable states. | `TODO` | — | — |
|
||
| I3-UI-04 | Complete WCAG-focused keyboard, focus, labels, icon names, and chart alternatives. | Web/accessibility evidence for representative critical pages. | `TODO` | — | — |
|
||
| I3-UI-05 | Add critical end-to-end flows across the integrated application. | Bootstrap/onboarding, Project/Task, attendance/correction/leave, and reports. | `TODO` | — | — |
|
||
| I3-UI-06 | Perform best-effort narrow-screen smoke checks only. | Prevent catastrophic corruption where practical; no mobile parity or mobile mockup gate. | `TODO` | — | — |
|
||
|
||
### 6.6 Iteration 3 integration gate
|
||
|
||
Integration order:
|
||
|
||
1. `work/platform`
|
||
2. `work/projects`, `work/tasks`, and `work/attendance` after their platform dependencies are available
|
||
3. `work/reports-ui`
|
||
|
||
Exit demonstration:
|
||
|
||
- Historical results and checkout cutoffs remain stable after later policy/calendar changes.
|
||
- Concurrent bootstrap, invitation/direct-add, membership exit/transfer, leadership, Task, leave, and correction operations fail safely.
|
||
- HTML, XLSX, and PDF expose identical authorized totals.
|
||
- Production refuses unsafe origin, proxy, datasource, or master-key configuration.
|
||
- The same non-root image works with bundled and external PostgreSQL.
|
||
- Work branches verify without publishing; only `main` publishes immutable SHA and convenience tags.
|
||
- SSH deployment remains dormant without secrets or an explicit enable variable.
|
||
- Desktop light/dark and accessibility acceptance passes; mobile/tablet remains best-effort only.
|
||
- Full integrated tests pass at the final integration commit.
|
||
|
||
## 7. Mandatory TDD workflow
|
||
|
||
Every feature follows this sequence:
|
||
|
||
1. Select a requirement and acceptance scenario.
|
||
2. Write the smallest behavioral test.
|
||
3. Run it and confirm the intended RED failure.
|
||
4. Record the RED command/result in the appropriate evidence file.
|
||
5. Write the minimum production code required for GREEN and add its meaningful Javadoc in the same implementation milestone.
|
||
6. Run the focused test.
|
||
7. Run the affected module/integration/web suite.
|
||
8. Refactor without weakening assertions.
|
||
9. Run the affected suite again.
|
||
10. Record final commands/results and commit SHA.
|
||
|
||
Recommended history:
|
||
|
||
```text
|
||
test(attendance): prove 09:00 check-in grace boundary [RED]
|
||
feat(attendance): enforce inclusive check-in grace boundary [GREEN]
|
||
```
|
||
|
||
The RED and GREEN commits may be pushed together after the branch head is green. The failing historical commit proves test-first order without leaving the remote branch intentionally broken.
|
||
|
||
Required evidence locations:
|
||
|
||
| Test level | Evidence directory |
|
||
|---|---|
|
||
| Unit/state/calculation | `docs/tests/unit/` |
|
||
| PostgreSQL/module integration | `docs/tests/integration/` |
|
||
| MockMvc/Thymeleaf/security web behavior | `docs/tests/web/` |
|
||
| Cross-module/browser journey | `docs/tests/e2e/` |
|
||
|
||
Every evidence Markdown record must include:
|
||
|
||
- requirement and scenario IDs;
|
||
- protected behavior and why it matters;
|
||
- test method and hand-derived expected result;
|
||
- exact RED command and relevant failure;
|
||
- exact GREEN and affected-suite commands/results;
|
||
- external dependency or environment boundaries;
|
||
- final commit SHA when available.
|
||
|
||
Javadoc is part of production implementation, not a later documentation phase. Every new or materially changed production type and every declared public/protected method shall document its business contract, including non-obvious authorization, transaction/locking, lifecycle/history, unit, timezone, or deadline semantics. Do not add prose that merely repeats names. Iteration 1 alone may retrofit Javadocs after feature implementation is complete; those branch-owned retrofit commits still require affected verification and independent scoped re-review. Every later iteration and turn shall add/update Javadocs during the implementation milestone.
|
||
|
||
## 8. Branch-level test emphasis
|
||
|
||
| Branch | Non-negotiable evidence |
|
||
|---|---|
|
||
| `work/platform` | Bootstrap concurrency, token lifecycle, account/security authorization, encryption, SMTP failure, session invalidation, production-profile failure. |
|
||
| `work/projects` | Lifecycle graphs, ownership, membership/invitation/exit/leadership intervals, transfer transactions, optimistic locking, guessed-ID denial. |
|
||
| `work/tasks` | Parameterized status graph, Leader/member creator/assignee distinction, self-Task and same-Project generic actors, daily-minute concurrency, progress totals. |
|
||
| `work/attendance` | Injected-Clock boundaries, PostgreSQL overlap/uniqueness, policy history, quota concurrency, schedulers and request-time guards. |
|
||
| `work/reports-ui` | MockMvc forms/authorization, accessible rendering, report query totals, XLSX/PDF parsing/parity, critical browser journeys. |
|
||
|
||
## 9. Iteration handoff protocol
|
||
|
||
At each iteration boundary:
|
||
|
||
1. Each branch owner updates every claimed item to `DONE`, `BLOCKED`, or returns it to `TODO`.
|
||
2. The owner provides commit SHA, evidence paths, exact verification commands, and remaining risk.
|
||
3. Integrate branches in the iteration's declared order.
|
||
4. Resolve cross-module conflicts through the owning branch rather than duplicating code in the integrator.
|
||
5. Run the full affected integrated suite.
|
||
6. Record the integration commit in Section 3.
|
||
7. Bring the integrated `main` into all five persistent work branches before the next iteration begins.
|
||
|
||
Handoff template:
|
||
|
||
```markdown
|
||
### <tracker ID> — <short title>
|
||
|
||
- Status: DONE | BLOCKED | TODO
|
||
- Owner:
|
||
- Requirements/scenarios:
|
||
- RED evidence:
|
||
- GREEN evidence:
|
||
- Focused verification:
|
||
- Affected-suite verification:
|
||
- Commit SHA:
|
||
- Remaining risk/blocker:
|
||
- Required next owner/action:
|
||
```
|
||
|
||
## 10. Global definition of done
|
||
|
||
A tracker item is complete only when:
|
||
|
||
- the numbered requirement and acceptance behavior are satisfied;
|
||
- the test existed and failed for the intended reason before production code;
|
||
- focused and affected suites pass;
|
||
- authorization and negative cases are covered where applicable;
|
||
- PostgreSQL-specific rules are tested against PostgreSQL, not H2;
|
||
- concurrency/deadline/history behavior has proportionate evidence;
|
||
- UI behavior uses server-side authorization and shared fragments;
|
||
- documentation/evidence paths are recorded in this tracker;
|
||
- new or changed production types and public/protected methods have accurate Javadoc created during implementation (Iteration 1 retrofit exception only);
|
||
- no unrelated files or another branch's ownership area were changed without coordination;
|
||
- the final branch head is green;
|
||
- integration does not alter totals, state graphs, or historical meaning.
|
||
|
||
## 11. Progress log
|
||
|
||
Append material coordination events only. Do not duplicate every commit.
|
||
|
||
| Date/time | Agent/person | Event | Tracker IDs | Evidence/commit | Next action |
|
||
|---|---|---|---|---|---|
|
||
| — | — | Plan initialized; no implementation item claimed. | — | — | Obtain requirements approval and begin Iteration 1. |
|
||
| 2026-08-15 | Taskmaster + five feature owners | Retrofitted targeted Lombok boilerplate after every owner fast-forwarded to the latest `main`; all five exact heads passed independent review and the combined merge passed 201 PostgreSQL 18.4 tests, compile, Javadoc/doclint, deterministic assets, and final integration review. | Iteration 1 maintenance | Platform `c9499732`; Project `58712710`; Task `469d7e27`; Attendance `5ddbd75f`; Reporting `8500cb6e`; integrated `b764707716f54ad164547b087f658c277cf46e0f`; `docs/tests/unit/lombok-*-boilerplate.md` | Push reviewed `main`, then fast-forward all five persistent work branches before Iteration 2 work. |
|