Lab Timesheet — Three-Iteration Delivery Plan
Artifact purpose: Local agent coordination and progress tracking
Implementation branches: work/platform, work/projects, work/tasks, work/attendance, work/reports-ui
Requirements authority: labtimesheet-docs-hub/requirements-specification.md
SRS: labtimesheet-docs-hub/software-requirements-specification.md
Initial status: Planning complete; implementation remains subject to requirements approval
This file divides the approved product scope across three iterations and five persistent work branches. It is a coordination artifact, not an alternative requirements source. When this plan and a numbered requirement disagree, the numbered requirement wins.
1. Progress rules
Use these exact status values:
| Status | Meaning |
|---|---|
TODO |
No implementation work has started. |
IN_PROGRESS |
One named owner is actively working on the item. |
BLOCKED |
Work cannot continue; the tracker must name the evidence and required decision/dependency. |
DONE |
Required RED/GREEN evidence exists, affected tests pass, and the integrated behavior satisfies the requirement. |
Before editing production code, an agent shall:
- Read the applicable numbered requirements and acceptance scenarios.
- Claim one bounded tracker item by setting its status to
IN_PROGRESSand recording owner/date. - Identify the test level and evidence file that will protect the behavior.
- Write and run the failing test before production code.
- Confirm the test fails because the required behavior is missing, not because the test or environment is broken.
When completing an item, the agent shall record:
- the exact RED command and expected failure;
- the exact GREEN and affected-suite commands;
- the evidence Markdown path under
docs/tests/; - the implementation commit or final local commit SHA;
- any remaining limitation that is explicitly allowed by the requirements.
No item becomes DONE based only on compilation, an isolated happy path, screenshots, or a verbal claim.
2. Branch ownership and conflict boundaries
| Branch | Sole or primary ownership |
|---|---|
work/platform |
Maven/application baseline, feature-package foundation, Flyway migration files, account/security/bootstrap, internship lifecycle, integration credential lifecycle, notification delivery infrastructure, Docker, and CI. |
work/projects |
Projects, membership intervals, invitations, membership-exit requests, leadership terms, Project lifecycle, Project-scoped authorization, member-removal orchestration, and Project completion. |
work/tasks |
Tasks, generic creator/assignment actors, member self-Task rules, comments, work logs, fixed status transitions, assignment/reassignment, Task soft deletion, and Project Task-progress calculations. |
work/attendance |
Attendance-policy versions, configured workdays, global calendar, HolidayAPI import interpretation, attendance, corrections, leave, deadline schedulers, and attendance/compliance metrics. |
work/reports-ui |
Shared Thymeleaf shell/fragments, Tailwind tokens/assets, dashboards, invitation/exit-request screens, shared report datasets, Chart.js presentation, XLSX/PDF exports, and cross-product UI/accessibility consistency. |
Conflict-prevention rules:
-
LabtimesheetApplicationshall remain incom.lab.labtimesheet, shared wiring inconfig, and business code infeature.account,feature.integration,feature.project,feature.task,feature.attendance,feature.notification, orfeature.reporting. Each feature repeats only the controller/model/model.dto/model.entity/repository/service/exception layers it needs, and tests mirror that feature/layer shape. -
Cross-feature code may call another feature's service contract and DTOs but shall not import that feature's repository or JPA entity. Do not create empty
utils,common, orcorepackages. -
Business persistence shall use Spring Data JPA repositories. Direct SQL is limited to Flyway migrations and schema/catalog verification; services shall not use
JdbcTemplateor embed SQL. -
work/platformownssrc/main/resources/db/migration/**, Maven/dependency configuration, Compose, container build files, and CI workflow files. Other branches request schema changes instead of independently allocating migration versions. -
work/reports-uiowns shared templates/fragments, shared design tokens, and general UI assets. Each domain branch owns its module-specific controllers and pages while consuming those shared fragments. -
work/tasksexposes focused Task query/transfer operations required by Project workflows.work/projectsowns the transaction that removes a member or completes a Project. -
work/platformowns HolidayAPI credential storage and the tested HTTP client.work/attendanceowns preview interpretation, selection, deduplication, import, and day-off effects. -
Attendance time and Task work time remain separate. No branch may make one mutate or prove the other.
-
Do not introduce a generic workflow engine, generic event-sourcing layer, multi-assignee Task model, Project-level day-off model, or speculative cross-module abstraction.
3. Iteration overview
| Iteration | Theme | Required demonstration | Status | Integration commit |
|---|---|---|---|---|
| 1 | Working vertical slice | Bootstrap users, create/activate Project, assign/change a Task, and check in/out with role-correct UI. | DONE |
b9b150ff8ca9333e3b46d77537ec91875a970d57 |
| 2 | Complete business workflows | Policy/calendar changes, leave/corrections, leadership/member transfer, work logs, notifications, and full HTML workflows. | TODO |
— |
| 3 | Hardening and delivery | Historical/concurrency proof, production security, HTML/XLSX/PDF parity, accessibility, containers, and CI publication boundary. | TODO |
— |
4. Iteration 1 — Working vertical slice
4.1 work/platform
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I1-PLAT-01 | Establish the Maven/Spring Boot modular baseline and root/config/feature package boundaries. | Context/load test; root-package and package-by-feature/layer check; no cross-feature repository/entity access or direct-SQL business services. | DONE |
platform_agent / 2026-08-15 | Approved Platform head 692b23e9b9891d360882671d8247965b44920b2f; integrated architecture/full-suite gates passed. |
| I1-PLAT-02 | Promote the reviewed 23-table/56-foreign-key PostgreSQL baseline into the platform-owned initial Flyway migration after explicit approval. | Fresh PostgreSQL 18.4 migration replay, catalog assertions, and invitation/exit same-Project constraints. | DONE |
platform_agent / 2026-08-15 | Fresh local replay produced exactly 23 application tables and 56 foreign keys at the integrated head. |
| I1-PLAT-03 | Configure PostgreSQL Testcontainers and shared test-only encryption/clock facilities. | Affected integration tests require no developer database or SMTP. | DONE |
platform_agent / 2026-08-15 | Taskmaster full PostgreSQL 18.4 Testcontainers suite passed 197/197. |
| I1-PLAT-04 | Implement atomic first-Admin bootstrap and permanent bootstrap closure. | Concurrent submissions create exactly one first Admin; restart keeps bootstrap closed. | DONE |
platform_agent / 2026-08-15 | Bootstrap/restart/concurrency evidence approved at 692b23e9b9891d360882671d8247965b44920b2f; fresh local bootstrap passed. |
| I1-PLAT-05 | Implement initial SMTP draft/test/active path sufficient for Mailpit onboarding. | Failed test cannot activate; tested revision supports delivery. | DONE |
platform_agent / 2026-08-15 | Real local Mailpit draft, test delivery, activation, active-state, and health checks passed at the integrated head. |
| I1-PLAT-06 | Create Mentor/Intern accounts, deliver activation, set first password, and authenticate/logout. | SMTP gate, single-use token, expiry, normalized email, role/state access. | DONE |
platform_agent / 2026-08-15 | Activation/authentication evidence and independent review approved at 692b23e9b9891d360882671d8247965b44920b2f. |
| I1-PLAT-07 | Provide development Compose with PostgreSQL and Mailpit plus initial Gitea verification workflow. | Fresh developer start and branch/main verification. | DEFERRED |
taskmaster / 2026-08-15 | Explicitly excluded from this exit gate; application containerization, Compose, and CI remain future work. |
4.2 work/projects
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I1-PRJ-01 | Atomically create a Mentor-owned PLANNED Project, eligible initial Leader membership, and first leadership term. |
No committed Project is empty or leaderless; non-owner, ineligible Leader, and guessed-ID access are denied. | DONE |
projects_agent / 2026-08-15 | Approved Project head baa0695c60153bc997ebf8b11adcfbdd2cbc1962; Project suite and review passed. |
| I1-PRJ-02 | Directly add eligible Interns through owning-Mentor-controlled interval memberships. | Multiple concurrent Projects per Intern; duplicate active membership rejected; no acceptance step for direct add. | DONE |
projects_agent / 2026-08-15 | Membership/eligibility/IDOR evidence approved at baa0695c60153bc997ebf8b11adcfbdd2cbc1962. |
| I1-PRJ-03 | Appoint and change one current Leader from active same-Project members. | One current Leader; non-member/ineligible selection rejected. | DONE |
projects_agent / 2026-08-15 | Leadership-term invariants and completed-history behavior approved at baa0695c60153bc997ebf8b11adcfbdd2cbc1962. |
| I1-PRJ-04 | Activate a Project when initial member, Leader, date, and assignee guards pass. | Missing Leader/member or invalid assignee blocks activation. | DONE |
projects_agent / 2026-08-15 | Task-bound activation guard approved at baa0695c60153bc997ebf8b11adcfbdd2cbc1962. |
| I1-PRJ-05 | Provide Project list/detail/member/leadership pages with owning-Mentor and member visibility. | MockMvc authorization plus direct-ID denial. | DONE |
projects_agent / 2026-08-15 | Authorized pages, retained errors, and former-member history approved at baa0695c60153bc997ebf8b11adcfbdd2cbc1962. |
4.3 work/attendance
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I1-ATT-01 | Resolve the seeded attendance policy, timezone, configured workdays, schedule, and separate check-in/checkout grace boundaries. | Both grace defaults are 30; values are 0–720; checkout cutoff must stay before local midnight. | DONE |
attendance_agent / 2026-08-15 | Approved Attendance head 01b8095e9459417e2cf5bd1079c796d4f01ec549; fresh seed verified both grace values at 30. |
| I1-ATT-02 | Manage manual future global calendar events and day-off decisions. | Admin-only mutation; past-event immutability; workday/day-off distinction. | DONE |
attendance_agent / 2026-08-15 | Calendar authorization and day-off evidence approved at 01b8095e9459417e2cf5bd1079c796d4f01ec549. |
| I1-ATT-03 | Check in once on an eligible day using server time and the effective policy. | Off-day, approved-leave, duplicate, lifecycle rejection, and inclusive 09:00 check-in-grace boundary. | DONE |
attendance_agent / 2026-08-15 | Boundary, eligibility, leave-day, and real duplicate-race evidence approved at 01b8095e9459417e2cf5bd1079c796d4f01ec549. |
| I1-ATT-04 | Check out once through the attached-policy checkout cutoff and derive basic daily classification. | Default 16:00 succeeds; first later instant and zero-grace late attempt fail; no checkout becomes only MISSING_CHECKOUT with raw checkout unchanged. |
DONE |
attendance_agent / 2026-08-15 | Historical-policy cutoff, eligibility recheck, and missing-checkout-only evidence approved at 01b8095e9459417e2cf5bd1079c796d4f01ec549. |
| I1-ATT-05 | Provide own-attendance history and authorized Mentor/Admin inspection. | Own/global-view authorization and historical applied-policy display. | DONE |
attendance_agent / 2026-08-15 | Policy-local history, all violations, and role authorization approved at 01b8095e9459417e2cf5bd1079c796d4f01ec549. |
4.4 work/tasks
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I1-TSK-01 | Create one-assignee Tasks in PLANNED or ACTIVE: any active member for self, current Leader for any active same-Project member. Store generic creator/assigner/assignee actors. |
Self-Task actor equality, other-assignee denial for members, Leader allowance, and cross-Project actor rejection. | DONE |
tasks_agent / 2026-08-15 | Approved Task head e38e2cdea912160b183c65398c4e8d5682c1b00e; actor/assignee/IDOR evidence passed review. |
| I1-TSK-02 | Validate optional due dates against Project dates and current global days off. | Boundary dates accepted; outside/day-off dates rejected. | DONE |
tasks_agent / 2026-08-15 | Due-date/calendar validation and retained field-error behavior approved at e38e2cdea912160b183c65398c4e8d5682c1b00e. |
| I1-TSK-03 | Enforce the complete fixed Task status graph through current-assignee authorization. | Parameterized allowed/forbidden transition matrix and ID denial. | DONE |
tasks_agent / 2026-08-15 | Server graph and legal UI choices approved at e38e2cdea912160b183c65398c4e8d5682c1b00e. |
| I1-TSK-04 | Add append-only Task comments for active members, current Leader, and owning Mentor. | Unauthorized/non-member and completed-Project mutation denial. | DONE |
tasks_agent / 2026-08-15 | Comment authorization, lock order, and completed-history behavior approved at e38e2cdea912160b183c65398c4e8d5682c1b00e. |
| I1-TSK-05 | Show Task list/detail and initial DONE/non-deleted progress/status counts. | Empty Project renders N/A; soft/deleted data not yet exposed as current. |
DONE |
tasks_agent / 2026-08-15 | Progress/N/A, assignee display, visibility, and dashboard ordering approved at e38e2cdea912160b183c65398c4e8d5682c1b00e. |
4.5 work/reports-ui
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I1-UI-01 | Establish Tailwind tokens and reusable Thymeleaf shell/fragments. | Fragment rendering, local assets, no unauthorized navigation items. | DONE |
reports_ui_agent / 2026-08-15 | Shared local-asset shell and persistent SMTP restriction contract verified at 039fe25c7c2622a015c8962892dd99ff58be321d. |
| I1-UI-02 | Implement the supported desktop sidebar/header, forms, tables, badges, alerts, confirmations, empty/error states, and theme bootstrap. | Keyboard labels/focus, no desktop page-level overflow, pre-paint theme application. | DONE |
reports_ui_agent / 2026-08-15 | Edge/Chromium 1365x900 focus, collapse tooltip, theme pre-paint, and overflow gates verified at 039fe25c7c2622a015c8962892dd99ff58be321d. |
| I1-UI-03 | Build basic Admin, Mentor, and Intern dashboards from real queries. | Role-correct metrics/actions; illustrative data never leaks into production paths. | DONE |
reports_ui_agent / 2026-08-15 | Public service/DTO dashboards and role-correct navigation verified at 039fe25c7c2622a015c8962892dd99ff58be321d. |
| I1-UI-04 | Integrate bootstrap, authentication, Project, Task, and attendance pages into the shared shell. | Critical MockMvc web flows and server-side authorization. | DONE |
reports_ui_agent / 2026-08-15 | Integrated shell, SMTP five-step journey, forms, history, errors, and authorization verified at 039fe25c7c2622a015c8962892dd99ff58be321d. |
4.6 Iteration 1 integration gate
Integration order:
work/platformwork/projectswork/attendancework/taskswork/reports-ui
Exit demonstration:
- First Admin bootstraps the installation.
- SMTP is tested through Mailpit.
- Admin creates and activates Mentor and Intern accounts.
- Mentor atomically creates a Project with its first Leader, directly adds another member, and activates it.
- Ordinary member creates a self-assigned Task; Leader creates and assigns another Task.
- Assignee changes Task status and comments.
- Intern checks in and checks out.
- Every role sees only authorized navigation, actions, and records.
- Full integrated tests pass at the iteration integration commit.
Taskmaster exit result (2026-08-15): DONE at main integration commit b9b150ff8ca9333e3b46d77537ec91875a970d57, incorporating reviewed candidate 039fe25c7c2622a015c8962892dd99ff58be321d and the verified development configuration/documentation follow-up. The final merged-main PostgreSQL 18.4 suite passed 197/197; Flyway produced 23 application tables and 56 foreign keys; Node 24/Tailwind assets built successfully; compile and full Javadoc/doclint passed on the reviewed candidate. A real local Java 25 process completed fresh bootstrap, login, five-step SMTP deferral, persistent restriction recovery, and a separate real Mailpit draft/test/activate flow with aggregate health UP. Temporary exit databases and Mailpit were removed; the existing development PostgreSQL service remained intact. Project/Task/Attendance role flows are protected by the approved branch suites and real desktop E2E evidence. Application containerization, Compose, CI, and production liveness/readiness hardening remain deferred as recorded above.
5. Iteration 2 — Complete business workflows
Iteration 2 starts only after every continuing branch incorporates the integrated Iteration 1 main.
5.1 work/platform
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I2-PLAT-01 | Complete account lock/unlock/deactivation and session invalidation. | State graph, authentication denial, retained attribution. | TODO |
— | — |
| I2-PLAT-02 | Implement activation failure/resend and forgot/reset-password workflows. | Failed token invalidation, single-use/expiry, generic enumeration-safe responses. | TODO |
— | — |
| I2-PLAT-03 | Implement internship start activation, completion, and withdrawal guards. | Scheduler plus request-time activation; Leader/unfinished-Task terminal guards. | TODO |
— | — |
| I2-PLAT-04 | Complete encrypted SMTP and HolidayAPI draft/test/active revision lifecycles. | AES-GCM round trip, wrong-key failure, one active revision, no browser secret disclosure. | TODO |
— | — |
| I2-PLAT-05 | Expose the tested VN HolidayAPI client to the attendance module. | Valid preview, invalid key/rate limit/unavailable responses without local-data outage. | TODO |
— | — |
| I2-PLAT-06 | Persist in-app notifications and initial ordinary-email delivery states, including Project invitation and membership-exit created/resolved types. | Recipient deduplication, domain commit independent of SMTP, self-Task silence, and UNAVAILABLE/sent/failed behavior. |
TODO |
— | — |
5.2 work/tasks
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I2-TSK-01 | Add dated 1–1440-minute Task work logs and author corrections. | Membership/date boundaries and author-only editing. | TODO |
— | — |
| I2-TSK-02 | Enforce the combined 1440-minute daily total across all Projects. | PostgreSQL integration and concurrent over-allocation proof. | TODO |
— | — |
| I2-TSK-03 | Reassign unfinished Tasks while preserving creator, state, comments, and work history and updating generic assignment actor/time. | DONE requires assignee reopen; creator attribution and prior logs/comments remain unchanged. | TODO |
— | — |
| I2-TSK-04 | Implement Task edit/soft deletion and authorized historical inspection for Leader and self-Task creator. | Leader controls any unfinished Task; creator controls only while still current assignee; deleted Task leaves normal progress but remains historical. | TODO |
— | — |
| I2-TSK-05 | Provide Task transfer and completion-query operations to the Projects module. | Atomic bulk transfer behavior and non-deleted/DONE counts. | TODO |
— | — |
| I2-TSK-06 | Complete Project status counts, percentage, total minutes, and per-member work queries. | Empty N/A, authorization scopes, hand-checkable totals. |
TODO |
— | — |
5.3 work/projects
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I2-PRJ-01 | Issue and revoke non-expiring Leader invitations while retaining the issuing leadership term. | Eligibility, one pending Project/Intern pair, Leader-own versus Mentor-any revocation, ordinary notification behavior. | TODO |
— | — |
| I2-PRJ-02 | Let only the intended authenticated Intern accept or decline; support Mentor direct-add supersession. | Email is not a bearer join token; exactly one membership; terminal status/code and provenance retained. | TODO |
— | — |
| I2-PRJ-03 | Create/cancel Leader-removal and member-leave requests without changing current rights. | Nonblank reason, same-Project/type shape, one pending request per target, requester-only cancellation. | TODO |
— | — |
| I2-PRJ-04 | Let only the owning Mentor approve/reject exits, using the assisted unfinished-Task transfer and Leader-replacement transaction. | Transfer/replacement/interval/request resolution commit together; reject/cancel changes request only. | TODO |
— | — |
| I2-PRJ-05 | Retain leadership history, change Leader without moving assignments, and complete only when every non-deleted Task is DONE. |
Exactly one current Leader in PLANNED/ACTIVE; completion closes intervals, revokes invitations, and supersedes exits. | TODO |
— | — |
| I2-PRJ-06 | Provide invitation, exit, former-member, and completed-Project historical read-only views. | Historical visibility and attribution without stale mutation authority. | TODO |
— | — |
5.4 work/attendance
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I2-ATT-01 | Schedule future-month attendance-policy versions, including separate grace values, and preserve effective history. | First-of-future-month rule; effective immutability; old checkout cutoff/report stability. | TODO |
— | — |
| I2-ATT-02 | Preview/import VN HolidayAPI candidates with Admin selection, override, provenance, and deduplication. | Public suggestion not authority; manual fallback; repeated import safety. | TODO |
— | — |
| I2-ATT-03 | Materialize frozen full-day leave allocations and monthly/cross-month quota reservations. | Workday/day-off classification, policy snapshot, quota per month. | TODO |
— | — |
| I2-ATT-04 | Implement leave submit/approve/reject/cancel and overlap protection. | Same-day boundary, pending/approved reservations, concurrent overlap/quota. | TODO |
— | — |
| I2-ATT-05 | Implement missed-checkout correction submission and effective-checkout derivation. | Reject before/at checkout cutoff; accept afterward through scheduled end +24 hours; raw checkout remains null. | TODO |
— | — |
| I2-ATT-06 | Implement Mentor approve/reject/revert and separate decision-window locking. | Valid state graph, concurrent decision, expired pending auto-rejection. | TODO |
— | — |
| I2-ATT-07 | Add idempotent schedulers and equivalent request-time deadline guards. | Late/multiple scheduler invocation cannot duplicate transitions/notifications. | TODO |
— | — |
5.5 work/reports-ui
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I2-UI-01 | Complete Admin/Mentor/Intern/Leader dashboards and notification UI. | Authorization-correct actions and deadline/state summaries. | TODO |
— | — |
| I2-UI-02 | Complete account, integration, Project, invitation, membership-exit, Task, policy/calendar, attendance, correction, and leave desktop workflows using shared fragments. | Leader invite/revoke/removal request, Intern accept/decline/leave/cancel, and Mentor exit decision forms retain safe input and expose conflicts clearly. | TODO |
— | — |
| I2-UI-03 | Build one authorized attendance/compliance HTML report dataset. | Date filters, detailed versus own scope, formulas and N/A. |
TODO |
— | — |
| I2-UI-04 | Build one authorized Project/Task HTML report dataset. | Project/member/status/date filters and per-member visibility rules. | TODO |
— | — |
| I2-UI-05 | Add only meaningful Chart.js trends with adjacent text/table alternatives. | Accessible label, equivalent data, theme tokens, reduced motion. | TODO |
— | — |
5.6 Iteration 2 integration gate
Integration order:
work/platformwork/taskswork/projectswork/attendancework/reports-ui
Exit demonstration:
- Admin schedules a future policy without changing historical output.
- Admin previews/imports holidays and overrides a suggested day-off decision.
- Intern submits cross-month leave and Mentor decides it.
- Intern submits a missed-checkout correction; Mentor decides and may revert it inside the window.
- Leader reassigns an unfinished Task while preserving work history.
- Leader invites an eligible Intern; the signed-in Intern accepts or declines; Mentor direct-add safely supersedes a pending invite.
- Mentor changes Leader without moving the former Leader's Tasks.
- Member requests to leave and Leader requests removal; Mentor rejects or approves through assisted transfer and required replacement.
- Mentor completes a Project after all non-deleted Tasks are done.
- Ordinary domain actions retain in-app notifications when SMTP is unavailable.
- Full integrated tests pass at the iteration integration commit.
6. Iteration 3 — Hardening, reports, and delivery readiness
Iteration 3 starts only after every continuing branch incorporates the integrated Iteration 2 main.
6.1 work/platform
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I3-PLAT-01 | Add normalized-email-plus-source-IP login throttling. | Five-in-15 and 15-minute throttle boundaries; successful-login clearing. | TODO |
— | — |
| I3-PLAT-02 | Finish ordinary email retry schedule and terminal failure handling. | Exact 1m/5m/30m/2h/12h attempts; idempotent bounded worker. | TODO |
— | — |
| I3-PLAT-03 | Add token cleanup and production-safe operational/status views. | Expired token behavior, no secret/stack/SQL disclosure. | TODO |
— | — |
| I3-PLAT-04 | Enforce production HTTPS/origin/proxy/header/cookie/master-key readiness. | Prod fails unsafe configuration; dev/test relax only transport/origin controls. | TODO |
— | — |
| I3-PLAT-05 | Produce the non-root application image and bundled/external PostgreSQL deployment modes. | Same immutable image becomes healthy in both configurations. | TODO |
— | — |
| I3-PLAT-06 | Finalize Gitea verification, main-only OCI publication, and disabled SSH deployment/rollback template. | Work branches never publish; disabled deploy receives no secrets; exact-SHA flow is testable when enabled. | TODO |
— | — |
6.2 work/projects
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I3-PRJ-01 | Harden concurrent membership, invitation acceptance/direct-add, exit approval, and leadership operations. | One valid winner; locks/rechecks cover invitation, Project, membership, leadership, request, and unfinished Tasks; stale requests produce explicit conflict without partial history. | TODO |
— | — |
| I3-PRJ-02 | Complete the global-role/context/ownership authorization matrix for direct membership, invitations, exits, and leadership. | Direct-ID, stale Leader, wrong invitee, cross-Mentor/member, requester, target, and decision-maker negative cases. | TODO |
— | — |
| I3-PRJ-03 | Prove completed/historical read-only behavior and terminal Intern guards. | No mutation through UI or direct request after lifecycle closure. | TODO |
— | — |
| I3-PRJ-04 | Verify Project list/progress query indexes and bounded performance. | Explain plan/catalog evidence for actual report paths. | TODO |
— | — |
6.3 work/tasks
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I3-TSK-01 | Harden concurrent status, reassignment, deletion, and daily-minute operations. | Optimistic conflicts and serialized daily total. | TODO |
— | — |
| I3-TSK-02 | Complete due-date impact behavior for later-created global days off. | Existing due date retained and disclosed; new/changed due date rejected. | TODO |
— | — |
| I3-TSK-03 | Complete former-assignee work-log correction and historical-deletion boundaries. | Author/member/Project lifecycle matrix. | TODO |
— | — |
| I3-TSK-04 | Complete Task authorization/ID-guessing matrix and progress query verification. | Admin/Mentor/Leader/member/creator/current-assignee distinctions, creator-right loss after reassignment, generic same-Project actors, and real query indexes. | TODO |
— | — |
6.4 work/attendance
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I3-ATT-01 | Finalize attendance-rate and compliance formulas plus N/A denominators. |
Hand-derived expected values across absence, leave, days off, and violations. | TODO |
— | — |
| I3-ATT-02 | Prove historical stability after workday, schedule, check-in/checkout grace, quota, penalty, and calendar changes. | Before/after report equality plus unchanged cutoff for an older attendance row. | TODO |
— | — |
| I3-ATT-03 | Harden concurrent leave quota/overlap and correction-decision races. | PostgreSQL exclusion plus transactional locking/optimistic conflicts. | TODO |
— | — |
| I3-ATT-04 | Prove request-time and scheduler equivalence at checkout/correction boundaries and both expiry windows. | Pre-cutoff correction rejection; inclusive submission deadline; delayed/repeated scheduler produces one final transition. | TODO |
— | — |
| I3-ATT-05 | Complete terminal-Intern and date-classification edge cases. | Terminal date with/without attendance, approved leave, and global day off. | TODO |
— | — |
6.5 work/reports-ui
| ID | Deliverable | Test/evidence emphasis | Status | Owner/date | Result/commit |
|---|---|---|---|---|---|
| I3-UI-01 | Export attendance/compliance and Project/Task datasets to XLSX. | Parse workbook and compare filters, rows, totals, and N/A with HTML. |
TODO |
— | — |
| I3-UI-02 | Export the same datasets to PDF through a print-safe template and embedded Unicode font. | Vietnamese sample text and HTML/XLSX/PDF total parity. | TODO |
— | — |
| I3-UI-03 | Complete desktop light/dark themes and all required desktop screens/states. | Theme before paint, system override, contrast, error/empty/stale/unavailable states. | TODO |
— | — |
| I3-UI-04 | Complete WCAG-focused keyboard, focus, labels, icon names, and chart alternatives. | Web/accessibility evidence for representative critical pages. | TODO |
— | — |
| I3-UI-05 | Add critical end-to-end flows across the integrated application. | Bootstrap/onboarding, Project/Task, attendance/correction/leave, and reports. | TODO |
— | — |
| I3-UI-06 | Perform best-effort narrow-screen smoke checks only. | Prevent catastrophic corruption where practical; no mobile parity or mobile mockup gate. | TODO |
— | — |
6.6 Iteration 3 integration gate
Integration order:
work/platformwork/projects,work/tasks, andwork/attendanceafter their platform dependencies are availablework/reports-ui
Exit demonstration:
- Historical results and checkout cutoffs remain stable after later policy/calendar changes.
- Concurrent bootstrap, invitation/direct-add, membership exit/transfer, leadership, Task, leave, and correction operations fail safely.
- HTML, XLSX, and PDF expose identical authorized totals.
- Production refuses unsafe origin, proxy, datasource, or master-key configuration.
- The same non-root image works with bundled and external PostgreSQL.
- Work branches verify without publishing; only
mainpublishes immutable SHA and convenience tags. - SSH deployment remains dormant without secrets or an explicit enable variable.
- Desktop light/dark and accessibility acceptance passes; mobile/tablet remains best-effort only.
- Full integrated tests pass at the final integration commit.
7. Mandatory TDD workflow
Every feature follows this sequence:
- Select a requirement and acceptance scenario.
- Write the smallest behavioral test.
- Run it and confirm the intended RED failure.
- Record the RED command/result in the appropriate evidence file.
- Write the minimum production code required for GREEN and add its meaningful Javadoc in the same implementation milestone.
- Run the focused test.
- Run the affected module/integration/web suite.
- Refactor without weakening assertions.
- Run the affected suite again.
- Record final commands/results and commit SHA.
Recommended history:
test(attendance): prove 09:00 check-in grace boundary [RED]
feat(attendance): enforce inclusive check-in grace boundary [GREEN]
The RED and GREEN commits may be pushed together after the branch head is green. The failing historical commit proves test-first order without leaving the remote branch intentionally broken.
Required evidence locations:
| Test level | Evidence directory |
|---|---|
| Unit/state/calculation | docs/tests/unit/ |
| PostgreSQL/module integration | docs/tests/integration/ |
| MockMvc/Thymeleaf/security web behavior | docs/tests/web/ |
| Cross-module/browser journey | docs/tests/e2e/ |
Every evidence Markdown record must include:
- requirement and scenario IDs;
- protected behavior and why it matters;
- test method and hand-derived expected result;
- exact RED command and relevant failure;
- exact GREEN and affected-suite commands/results;
- external dependency or environment boundaries;
- final commit SHA when available.
Javadoc is part of production implementation, not a later documentation phase. Every new or materially changed production type and every declared public/protected method shall document its business contract, including non-obvious authorization, transaction/locking, lifecycle/history, unit, timezone, or deadline semantics. Do not add prose that merely repeats names. Iteration 1 alone may retrofit Javadocs after feature implementation is complete; those branch-owned retrofit commits still require affected verification and independent scoped re-review. Every later iteration and turn shall add/update Javadocs during the implementation milestone.
8. Branch-level test emphasis
| Branch | Non-negotiable evidence |
|---|---|
work/platform |
Bootstrap concurrency, token lifecycle, account/security authorization, encryption, SMTP failure, session invalidation, production-profile failure. |
work/projects |
Lifecycle graphs, ownership, membership/invitation/exit/leadership intervals, transfer transactions, optimistic locking, guessed-ID denial. |
work/tasks |
Parameterized status graph, Leader/member creator/assignee distinction, self-Task and same-Project generic actors, daily-minute concurrency, progress totals. |
work/attendance |
Injected-Clock boundaries, PostgreSQL overlap/uniqueness, policy history, quota concurrency, schedulers and request-time guards. |
work/reports-ui |
MockMvc forms/authorization, accessible rendering, report query totals, XLSX/PDF parsing/parity, critical browser journeys. |
9. Iteration handoff protocol
At each iteration boundary:
- Each branch owner updates every claimed item to
DONE,BLOCKED, or returns it toTODO. - The owner provides commit SHA, evidence paths, exact verification commands, and remaining risk.
- Integrate branches in the iteration's declared order.
- Resolve cross-module conflicts through the owning branch rather than duplicating code in the integrator.
- Run the full affected integrated suite.
- Record the integration commit in Section 3.
- Bring the integrated
maininto all five persistent work branches before the next iteration begins.
Handoff template:
### <tracker ID> — <short title>
- Status: DONE | BLOCKED | TODO
- Owner:
- Requirements/scenarios:
- RED evidence:
- GREEN evidence:
- Focused verification:
- Affected-suite verification:
- Commit SHA:
- Remaining risk/blocker:
- Required next owner/action:
10. Global definition of done
A tracker item is complete only when:
- the numbered requirement and acceptance behavior are satisfied;
- the test existed and failed for the intended reason before production code;
- focused and affected suites pass;
- authorization and negative cases are covered where applicable;
- PostgreSQL-specific rules are tested against PostgreSQL, not H2;
- concurrency/deadline/history behavior has proportionate evidence;
- UI behavior uses server-side authorization and shared fragments;
- documentation/evidence paths are recorded in this tracker;
- new or changed production types and public/protected methods have accurate Javadoc created during implementation (Iteration 1 retrofit exception only);
- no unrelated files or another branch's ownership area were changed without coordination;
- the final branch head is green;
- integration does not alter totals, state graphs, or historical meaning.
11. Progress log
Append material coordination events only. Do not duplicate every commit.
| Date/time | Agent/person | Event | Tracker IDs | Evidence/commit | Next action |
|---|---|---|---|---|---|
| — | — | Plan initialized; no implementation item claimed. | — | — | Obtain requirements approval and begin Iteration 1. |
| 2026-08-15 | Taskmaster + five feature owners | Retrofitted targeted Lombok boilerplate after every owner fast-forwarded to the latest main; all five exact heads passed independent review and the combined merge passed 201 PostgreSQL 18.4 tests, compile, Javadoc/doclint, deterministic assets, and final integration review. |
Iteration 1 maintenance | Platform c9499732; Project 58712710; Task 469d7e27; Attendance 5ddbd75f; Reporting 8500cb6e; integrated b764707716f54ad164547b087f658c277cf46e0f; docs/tests/unit/lombok-*-boilerplate.md |
Push reviewed main, then fast-forward all five persistent work branches before Iteration 2 work. |